• Location: Richmond, Virginia
  • Size: 51 MW
  • Budget: $938,000
  • Project: RVA3, Acceptance Testing
Description: EPS performed NETA acceptance testing for a new data center facility, utilizing two teams of technicians. One team covered NETA testing of all MV equipment on site and another team tested LV equipment at a local fabrication facility where electrical distribution equipment was staged and shipped to site for final installation. A thorough review of all protective device settings was performed during the closeout of the LV 4 commissioning process adhering to the manufacturer coordination study.