• Location: Atlanta, Georgia
  • Size: 970,000 sq.ft. total enclosed space
    •           531,000 sq.ft. Data Center footprint
    •           120MWs of Critical Power Capacity
  • Budget: $67,459.00
  • Project: Hybrid Colo 1 & 2, Acceptance Testing
Description: EPS performed NETA acceptance testing services for QTS’ new data center, ATL1-DC2. This job includes low – medium voltage electrical distribution installation with switchgears, emergency gensets, ATS, power quality meters, surge protection, cables up to the static switches, and PDUs inside the data halls.