• Location: Quincy, Washington
  • Size: 24.5 MW
  • Budget: $550,000
  • Project: MWH06
Description: The EPS team performed testing and startup for all of the utility infrastructure systems which included, primary and distribution substations. Equipment tested included grounding, 15 kV switchgear, distribution transformers, protective relays, metering devices, instrument transformers, medium voltage vacuum circuit breakers, medium voltage cables, medium voltage surge arresters, low voltage switchgear, low voltage dry type transformers, metal enclosed busways, low voltage power circuit breakers, low voltage molded case circuit breakers, low voltage panelboards, low voltage switches, and thermographic surveys.